The bottleneck for AI data centers is power, not chips
How fast is demand rising, and is round-the-clock power supply keeping up? We check it step by step with actual data.
Choose a region
Tap a state to select its grid operator (ISO)The map is simplified to states. Real ISO borders differ from state lines; states spanning several ISOs are shown under one main ISO.
Power demand in ERCOT is accelerating, and round-the-clock power additions are not keeping pace
Evidence level: Actual what already happened · Official forecast grid operator forecast · Request requests for the future (incl. duplicates)
AI data center power demand is really accelerating
Average power demand added since 2019
ActualAverage power demand in ERCOT grew +1.2%/yr in 2019~2021 (incl. the COVID period), but has sped up to +5.4%/yr over the last 5 years. Compared with 2019, average demand is up 14.3 GW — the output of about 10 nuclear reactors running around the clock.
- Bars show the change from 2019 average demand (set to zero). One nuclear reactor = 1.4 GW.
Commercial electricity sales (2016=100)
ActualData center power is mostly counted as commercial use. Texas commercial sales grew +4.8%/yr over the last 5 years, faster than the US average (+3.2%/yr).
The same 2030 peak demand forecast, by year published
Official forecastThe latest forecast (published 2025) puts 2030 peak demand at 139 GW. Once earlier vintages are added, the upward revisions will show.
Source: 2025 ERCOT System Planning Long-Term Hourly Peak Demand and Energy ForecastLarge-load interconnection requests
RequestRequests to connect in the future total 474 GW. They include duplicate and speculative requests, so treat this as a reference indicator only.
US data center construction spending (seasonally adjusted annual rate)
ActualIn 2026-09, data center construction spending ran at $96.5B annualized, compared with $49.2B for general offices. The pace of building is the pace of power demand.
Actual additions of round-the-clock power are not nearly as large
Net additions by year (added − retired)
ActualOf 34.5 GW net added over the last 3 years, only 0.1 GW can supply power around the clock. The rest is solar, batteries and other sources whose output depends on weather and time of day.
Generation queue — requests to build
RequestThe 446 GW queue is a list of requests to build. Of that, 93 GW is round-the-clock power, and being in the queue does not mean it will be built.
What is actually generating power now (last 30 days)
ActualSo the grid's margin is shrinking
Cumulative since 2019: peak demand growth vs net additions
ActualSince 2019, peak demand has changed by +16.5 GW, and round-the-clock power has grown by 3.8 GW. Demand growth is outpacing additions of round-the-clock power.
- Peak demand depends heavily on that year's weather (heat waves, cold snaps). Look at the trend rather than a single year.
- Solar and batteries also help somewhat at peak hours, but their output varies with weather and time, so they are shown separately.
Reserve margin forecast
Official forecastIf the operator's forecast holds, the reserve margin turns negative from 2028, meaning there would not be enough generation to meet expected peak demand.
The shortage is showing up in prices and behavior
ERCOT has no capacity market
NoteERCOT is an 'energy-only market': there is no capacity market that prices future supply in advance, only real-time power prices. So scarcity shows up as real-time price spikes rather than a capacity price. Since it cannot be compared in one number like PJM or MISO capacity prices, we suggest reading the commercial rates below together with the reserve margin forecast in step 3.
Source: ERCOT market designCommercial electricity price (annual avg, ¢/kWh)
ActualTexas commercial rates are +0.1% over the last 12 months versus the prior year. Fuel costs and other factors also play a role.
Are orders flowing to those who ease the bottleneck?
Evidence instead of recommendations. We collect contracts that power equipment and generation companies actually signed in the US, and their order backlogs, based on original filings.
Korea's power equipment exports to the US (by product, annual)
ActualKorea's transformer exports to the US were $1,815M over the last 12 months, +12.8% versus the prior year. It is the earliest sign of whether US grid build-out is flowing into Korean companies' results.
- Korea-wide exports by customs product code (HS), not any single company's results. Transformers 850421–23, switchgear and panels 8535/8537, cables 8544, generators 8502 and gas turbines 841182.
US & North America supply contract filings (DART)
ActualOver the last 12 months, Korean power equipment and generation companies disclosed 31 US/North America supply contracts worth ₩4,713.6bn. Counterparties and amounts are taken as filed.
| Filed | Company | Counterparty | Region | Value | % of revenue | Term |
|---|---|---|---|---|---|---|
| 2026-11-10 | HD Construction Equipment (engines) | Power Solutions International Inc | US | ₩165.5bn | 4.4% | 2027-01-01 ~ 2028-12-31 ↗ |
| 2026-10-29 | Sanil Electric | Undisclosed (trade secret) | US | ₩32.6bn | 6.5% | 2026-10-21 ~ 2032-12-11 ↗ |
| 2026-10-19 | LS ELECTRIC | LS ELECTRIC AMERICA Inc. | US | ₩168.9bn | 3.4% | 2026-10-16 ~ 2027-12-31 ↗ |
| 2026-10-15 | Taihan Cable & Solution | TAIHAN ELECTRIC USA LTD. | US | ₩116.8bn | 3.2% | 2026-10-14 ~ 2028-12-31 ↗ |
| 2026-10-13 | LS ELECTRIC | LS ELECTRIC AMERICA Inc. | US | ₩185.3bn | 3.7% | 2026-10-12 ~ 2027-07-05 ↗ |
| 2026-10-07 | HD Construction Equipment (engines) | Enchanted Rock | US | ₩387.9bn | 10.3% | 2027-01-01 ~ 2028-12-31 ↗ |
| 2026-10-06 | Sanil Electric | Undisclosed (trade secret) | US | ₩35.1bn | 7.0% | 2026-09-22 ~ 2032-09-13 ↗ |
| 2026-10-01 | LS ELECTRIC | LS ELECTRIC AMERICA Inc. | US | ₩181.2bn | 3.6% | 2026-09-30 ~ 2030-01-30 ↗ |
| 2026-09-30 | LS Corp. (LS Cable) (subsidiary filing) | LS Cable Systems America Inc. | US | ₩236.3bn | 3.5% | 2026-02-09 ~ 2030-04-13 ↗ |
| 2026-09-15 | Hyosung Heavy Industries | HICO America Sales & Tech,Inc. | US | ₩166.5bn | 2.8% | 2026-09-14 ~ 2028-08-31 ↗ |
| 2026-08-24 | LS ELECTRIC | LS ELECTRIC AMERICA Inc. | US | ₩230.9bn | 4.7% | 2026-06-08 ~ 2027-01-30 ↗ |
| 2026-08-20 | Sanil Electric | TMEIC USA | US | ₩51.2bn | 10.2% | 2026-08-17 ~ 2027-08-26 ↗ |
| 2026-07-31 | HD Hyundai Electric | HD Hyundai Electric America Corporation | US | ₩61.9bn | 2.9% | 2023-11-30 ~ - ↗ |
| 2026-07-21 | SNT Energy | JGC FLUOR BC LNG II JV(LNG Canada Project Phase 2) | 해외 | ₩31.9bn | 5.3% | 2026-07-21 ~ 2027-11-17 ↗ |
| 2026-05-14 | LS ELECTRIC | LS ELECTRIC AMERICA Inc. | US | ₩319.0bn | 6.4% | 2026-04-28 ~ 2027-03-29 ↗ |
| 2026-05-07 | HD Hyundai Electric | HD Hyundai Electric America Corporation | US | ₩173.0bn | 4.2% | 2026-05-06 ~ 2029-08-31 ↗ |
| 2026-04-30 | Sanil Electric | Bloom Energy | US | ₩50.3bn | 10.0% | 2026-04-24 ~ 2027-03-29 ↗ |
| 2026-04-13 | LS ELECTRIC | LS ELECTRIC AMERICA Inc. | US | ₩170.3bn | 3.4% | 2026-04-10 ~ 2026-12-31 ↗ |
| 2026-04-07 | Iljin Electric | ILJIN Electric USA | Canada | ₩51.8bn | 2.5% | 2026-04-06 ~ 2028-12-31 ↗ |
| 2026-03-06 | Doosan Enerbility | Undisclosed (trade secret) | US | — | — | 2026-03-06 ~ 2029-11-30 ↗ |
- Only disclosed contracts appear (mandatory above roughly 5–10% of revenue; smaller voluntary filings included). Contracts with a counterparty withheld as a trade secret are included if the sales region is the US or North America.
Order backlog (latest periodic report)
ActualBacklog is orders already won but not yet booked as revenue. A growing backlog means results are locked in for years ahead.
- Figures read by AI with verbatim quotes from each company's latest quarterly/semiannual/annual report ('Sales and orders') and checked by an admin. They may include non-US orders and non-power businesses.
- A holding or parent company's backlog is a group figure that already includes its subsidiaries. To avoid double counting, LS ELECTRIC·Gaon Cable are left out of the total.
US power equipment & generation companies: backlog (RPO) vs revenue
ActualFor the same 3 companies since 2023Q4, backlog is up +177.6% while revenue is up +66.0%: orders are piling up faster than they turn into sales.
- RPO (remaining performance obligation) is contracted value not yet recognized as revenue. Its scope differs by company (some include long-term service agreements), so compare each company's growth rather than amounts. Caterpillar and Cummins are mostly non-power businesses, so they appear in the earnings table below with power-segment figures instead.
US companies' latest earnings (orders, backlog, gas turbines)
ActualGE Vernova's gas turbine reservations and backlog stand at 122 GW (as of 2026-09-30). Anyone wanting a new US gas plant now waits years for turbines.
| Quarter end | Company | Orders | Backlog | Gas turbines | Power segment & data centers |
|---|---|---|---|---|---|
| 2026-09-30 | Caterpillar | — | — | — | Power & Energy 3분기 매출은 87.84억 달러(전년 동기 74.63억 달러, +18%)였고, 이 중 발전(Power Generation) 매출은 34.21억 달러로 전년 26.34억 달러 대비 30% 증가했습니다. 발전 부문 매출 증가는 주로 데이터센터 용도의 터빈 및 터빈 관련 서비스와 대형 왕복엔진에서 나왔다고 언급했으나 구체적인 데이터센터 수치는 없습니다. ↗ |
| 2026-09-30 | GE Vernova | $29.3B | $197.0B | 122 GW | Power 부문 3분기 수주는 217.8억 달러(전년 대비 +178%), 매출은 60.67억 달러(+25%)였고 가스터빈 수주잔고는 53GW에서 64GW로 늘었다. 데이터센터 고객을 위한 신규 솔루션 개발을 언급했지만 데이터센터 관련 수치는 제시하지 않았다. ↗ |
| 2026-09-30 | Eaton | — | — | — | 전기부문 수주(12개월 롤링 평균, 유기적): 전기 아메리카 +39%, 전기 글로벌 +51%이며, 백로그는 각각 전년 대비 +33%, +121% 증가했고 전기 부문 전체 백로그는 +46%입니다. Boyd Thermal(데이터센터용 열관리)이 전기 글로벌 매출을 31% 끌어올렸고, 데이터센터·유틸리티 수요 대응을 위해 COL Group을 9.21억 달러에 인수하기로 했습니다. ↗ |
| 2026-09-30 | Quanta Services | — | $63.7B (+62.7%) | — | 전력·송전망 중심의 Electric 부문 3분기 매출은 98.00억 달러(전년 61.72억 달러)였고, 백로그는 518.85억 달러(전년 326.44억 달러)입니다. 데이터센터를 별도로 언급한 수치는 없으며, 유틸리티·발전·산업·기술 고객 전반으로 수요가 확대되고 있다고만 서술했습니다. ↗ |
| 2026-09-30 | Cummins | — | — | — | 파워시스템 부문 3분기 매출 23억 달러(+15%), 발전(Power generation) 매출 1,557백만 달러(전년 1,280백만 달러), 부문 EBITDA 마진 25.4%이며, 주문·수주잔고는 공개되지 않았다. CEO는 데이터센터 구축으로 글로벌 발전설비 수요가 매우 강하다고 밝혔고, 대형 미국 데이터센터 프로젝트에 BESS를 공급하기로 선정되었다(수치 없음). ↗ |
| 2026-09-30 | Hubbell | — | — | — | 전력 부문 수주·매출·수주잔고의 수치는 없고, Electrical Solutions 매출이 8.45억 달러(+51%, 유기 +22%)로 증가했다고만 기재됨. CEO가 Electrical Solutions의 유기적 성장률 20% 초과가 강한 데이터센터 시장에 힘입은 것이라고 언급했으나 구체적 수치는 없음. ↗ |
| 2026-09-30 | MasTec | — | $24.5B (+46.3%) | — | 전력 공급(Power Delivery) 부문 3분기 매출은 1,835.2백만 달러(전년 대비 +65.2%), 18개월 백로그는 8,913백만 달러로 전년 5,128백만 달러 대비 약 74% 증가했습니다. 데이터센터를 직접 언급하지는 않았으나, 유틸리티 및 대규모 부하(large-load) 인프라 수요가 강하고 AI 기반 데이터 소비 증가에 대응한 통신 인프라 투자 필요성을 언급했습니다. ↗ |
| 2026-09-30 | Generac | — | $4.5B | — | C&I 부문 3분기 총매출은 553.0백만 달러로 전년 동기 432.4백만 달러 대비 약 28% 증가했으며, 데이터센터 매출 증가가 주요 원인이다. 데이터센터향 제품 백로그가 약 45억 달러로 증가했고, 아마존과의 계약에 따라 2027~2028년 인도 예정 규모는 합계 24억 달러이다. ↗ |
| 2026-06-30 | Powell Industries | $934M (+158.0%) | $2.4B (+71.4%) | — | 분기 중 4억 달러 초과 규모의 데이터센터 메가 오더(behind-the-meter 현장 발전설비 설계 관련)를 수주했다. ↗ |
- Figures read by AI with verbatim quotes from SEC 8-K earnings exhibits and checked by an admin. Brackets show change vs the same quarter a year earlier.
Frequently asked questions
Why is power the bottleneck for AI data centers?
Data centers draw power almost constantly, around the clock. Solar and wind, whose output changes with weather and time of day, cannot carry that alone; round-the-clock sources like gas and nuclear must grow too. Chips arrive in months, but power plants and transmission take years, so the bottleneck is supply failing to keep pace with demand. This page compares the two speeds with actual data.
What are ERCOT, PJM and MISO?
They are independent system operators (ISOs) that run parts of the US power grid. ERCOT covers most of Texas; PJM covers 13 eastern states and Washington, DC, including Virginia, the world's largest data center hub; MISO covers 15 Midwestern and Southern states. All three are seeing fast growth in data center connection requests.
What does a rising capacity price mean?
A capacity price is set by auction to secure the power supply needed a few years ahead. The more it rises, the more the market believes future supply margins are thin, and it eventually feeds into electricity bills. PJM and MISO have capacity markets; ERCOT does not, so scarcity shows up as real-time price spikes instead.
Where does the data come from, and how often is it updated?
We use the US Energy Information Administration's (EIA) hourly demand and generation, monthly generator inventory (EIA-860M) and retail sales, each ISO's interconnection queues and reports, and US Census construction spending. EIA figures are collected automatically every day; ISO report figures are extracted by AI with verbatim quotes whenever they are published and posted after admin review.
This page organizes public statistics and reports and is not investment advice. Figures are collected automatically and may lag depending on when the original data is released. This page was translated from the Korean original; if wording differs, the Korean page prevails.